GEORGE NEWS - While the contractor appointed to build the new high school in George East has moved on site to start the construction, a group of concerned residents are circulating a petition letter and are considering an urgent court application to halt the project.
These concerned residents say they have been kept in the dark about the details of the Western Cape Education Department's (WCED) project right up to a public information meeting at Pine Lodge on Monday evening, 16 November, on the eve of the construction commencement date.
Adv Gert van Niekerk, a nearby resident, said the meeting was "window-dressing". "We have been kept guessing while the planning process of a huge project in our midst was under way."
The concerned group is questioning the location of the school, traffic impact and an apparent lack of public consultation and transparency during the building application. The sports fields are located right opposite the Genevafontein Retirement Village, and the school's main entrance is some 100m from Genevafontein's in Stander Street.
A resident speaking anonymously on behalf of the concerned group said the impact of a new school on the surrounding neighbourhood has not been adequately addressed.
"When we bought our property 38 years ago, we knew a primary school was planned for the area, but everything has changed since then. Development in the surrounding area has increased exponentially, Glenwood School was built and the population density increase has been significant."
She said the affected community has been unable to access planning documents such as the traffic impact study. "We are wondering if current conditions and the growth of the area were considered. What about the safety of learners who may have to cross busy roads to reach the school?"
Another ratepayer speaking anonymously on behalf of the Ward 18 committee confirmed this frustration. She said the committee had approached the municipality and Western Cape authorities as early as May for more information, but had received no response.
“If the community had been consulted properly and timeously, I believe there would have been no uproar.”
She used Oranjezicht in Cape Town as an example where a severe ‘school run gridlock’ has been impacting surrounding suburban streets after expansions to the St Cyprian School campus. “Residents’ pro-active warnings to authorities were ignored and traffic calming measures promised by the municipality during the development planning stage came to nought due to funding delays,” she said.
An architect's rendition of the new school that is to be built at a cost of R135m. Image: WCED
Van Niekerk said he is not against the school, but there are three high schools in a 1km radius from the building site.
"Loerie Park will not be feeding the new school, so children will have to be transported from areas such as Pacaltsdorp, where residents have been promised a second high school and where land is available. How affordable will transport be for those parents?"
The use of local labour is another issue. Residents are calling for jobs to be prioritised for Georgians.
The concerned group's spokesperson said over 300 residents arrived at the meeting expecting an opportunity to raise their concerns, only to be told that construction was due to begin the following day.
"We have started a petition and are consulting legal representatives about a possible interdict," she said.
George Herald is awaiting comment from the WCED and George Municipality.
The WCED said earlier that the school was expected to open in 2029. It will accommodate up to 1 120 learners, with 30 standard and four specialist classrooms. It has a strong focus on science, technology, engineering and mathematics (Stem).
H & I Construction, that was involved in the recent upgrading of the George water treatment works, is the building contractor.